Pilot plant to production: the program, in order
-
Prove it at the pilot plant.
I stood up the experimental production site, a full-scale glass plant instrumented with hundreds of sensors and connected devices, to prove the technology for scale-up.
-
Pick up the scale-up.
I came back to 12 portfolio teams, 200+ engineers, and three facilities. One production plant was already in flight when I took it on.
-
Gate every stage.
Every stage closed with signoffs and demos. Construction and commissioning ran Waterfall, anything software ran Agile, and hardware startup and configuration ran hybrid.
-
Integrate the vendors.
Dozens of vendors needed onboarding, data access, and system configuration. I qualified each vendor-built system, validated each control loop into SCADA, ran QA validation, and trained engineers to operate the systems and check the vendor’s work. Testing ran on a segregated copy in a test environment, so tests did not touch production.
-
Plan the people and the assets.
I forecasted engineering headcount, built the capacity model for every asset, and interviewed and hired for the team. Every asset had a BOM, and cost, depreciation, risk, and ROI were reported through SAP and Microsoft Project.
-
Run the work in one place.
A templated Azure DevOps intake saved 8 hours a week per person on a 12-person IT team. A ticketing and service management system cut launch time from a month to under a week. A QA validation standard took project timelines from 25 days to 4 and became the organization’s standard.
-
Hand over the knowledge.
I migrated the DITA XML knowledge base to a new platform with Okta SSO for 10,000+ users, live on schedule with adoption up 5x, and rolled out Microsoft Copilot to 300 engineers, cutting onboarding time 35%.